DORIS III Operating Schedule 2011/2012

(Version: November 4, 2011)


General Information

Start and End

7h

each beamtime

Additional Machine Studies

8 - 17h    

on Wednesdays
except for the last week
of each beamtime block

Two-bunch mode 2012

 

nothing scheduled so far


2011 / 2nd half

Beamline Commissioning

15.08.11

1 day

4. Beamtime

16.08.11 - 12.09.11
no user operation on 01.09.11

26 days

Machine Studies/Maintenance

12.09.11 - 19.09.11

7 days

5. Beamtime

19.09.11 - 24.10.11

35 days

Machine Studies/Maintenance

24.10.11 - 31.10.11

7 days

6. Beamtime

31.10.11 - 21.12.11

50 days

Winter shutdown

21.12.11 -

 


2012 / 1st half

Beamline Commissioning

27.02.12 - 29.02.12

2 days

1. Beamtime

29.02.12 - 16.04.12

48 days

Machine Studies/Maintenance

16.04.12 - 23.04.12

7 days

2. Beamtime

23.04.12 - 04.06.12

42 days

Machine Studies/Maintenance

04.06.12 - 11.06.12

7 days

3. Beamtime

11.06.12 - 23.07.12

42 days

Machine Studies/Maintenance

23.07.12 - 30.07.12

7 days


2012 / 2nd half

   

4. Beamtime

30.07.12 - 10.09.12

42 days

Machine Studies/Maintenance

10.09.12 - 17.09.12

7 days

5. Beamtime

17.09.12 - 22.10.12

35 days

End of DORIS III
synchrotron operation

22.10.12

 

 